Water Well Project No. 4: Barabarani Village, Kangani, Pemba South Region, Zanzibar, Tanzania

THE IMPACT

Our Impact in Barabarani

~ 250 - 300

People Benefited

4

Communities Served

1

Borehole Well

5,000L

Water Storage Capacity

What this project delivered

Elevated water tower

Water distribution station

Water pipelines

Electricity connection

Project Overview

For residents of Barabarani and neighboring communities, securing water was closely tied to the seasons because the area lacked a dependable government water supply.

During the rainy season, villagers often collected water from natural depressions and low-lying areas where rainwater accumulated. When the dry season arrived, these temporary sources dried up, leaving families with very limited options for obtaining water.

To create a more dependable year-round source, Humanity for All constructed a water well, installed a 5,000-liter water storage tank and water distribution station, installed and extended water distribution pipelines, and provided an electricity connection to support the water system.

Community Impact

The new water system has changed how residents meet one of their most essential daily needs. Instead of depending heavily on temporary rain-fed sources that disappear during dry periods, families now have a more dependable source of water available within the area.

This improvement is particularly meaningful for women, children, people with disabilities, and others who may have greater difficulty traveling to obtain and carry water.

Through the well and its distribution pipelines, the project is helping residents of Barabarani and neighboring communities maintain better access to water throughout the year.

Sadaqah Jariyah

This water project was generously funded by Aziz Salim Said as a Sadaqah Jariyah (ongoing charity) in memory of his late wife, Ibiyinka Kudiratu Molade Said.

May this ongoing charity continue to benefit the communities it serves, honor her memory, and be a source of continuous blessings and reward for her.

Location

Barabarani Village, Kangani, Pemba South Region, Zanzibar, Tanzania

Project Status

Completed

Completion Date

August 1, 2025

Funding

Water Well Project No. 4 was made possible through the generous support of Aziz Salim Said in memory of his late wife, Ibiyinka Kudiratu Molade Said.

Project Documentation

Photos and video from the project are available to document the completed water system and its impact on the community.

Join us in creating a more compassionate and equitable world.

Because humanity belongs to all.